Friday, June 12, 2015

Remaining Storm Sewer Repairs, Concrete Curb & Gutter, and Asphalt Paving Scheduled for Next Week.

Work Completed Last Week:
Concrete Curb & Gutter and Sidewalk Replacement (Schroeder & Schroeder):
·         Completed concrete sidewalk and curb & gutter replacement on Mohawk Lane, Vantage Lane, and Greenbriar Drive
·         Greenbriar Drive - Driveway replacements
·         Church Street – Glenview Road to Dewes Street 

Storm Sewer Improvements (DiVinci)
·         No work completed.

Asphalt Pavement Paving (JA Johnson Paving)
·         Vantage Lane – Pfingsten Road to East End, including Cul-de-Sacs
·         Brookdale Lane – Landwehr Road to West End
·         Greenbriar Drive – Lotus Lane to Warren Road (1st Layer)
·         Harmony Lane – Waukegan Road to west end (1st Layer)

Asphalt Pavement Removal and Paving (JA Johnson Paving)
·         Alley north of Colfax Avenue, west of Waukegan Road.
·         Minor patching throughout the Village.

Work Anticipated Next Week:
Concrete Curb & Gutter Replacement (Schroeder & Schroeder):
·         Huber Court – Huber Lane to East End

Storm Sewer Improvements (DiVinci)
·         Huber Court – Huber Lane to East End
·         Church Street – Glenview Road to Dewes Street
·         Country Lane – Central Parkway to Longvalley Road 

Asphalt Pavement Paving (JA Johnson Paving)
·         Country Lane – Central Parkway to Longvalley Road
·         Church Street – Glenview Road to Dewes Street
·         Huber Court – Huber Lane to East End
·         Greenbriar Drive – Lotus Lane to Warren Road (2nd Layer)
·         Harmony Lane – Waukegan Road to west end (2nd Layer)

Landscape Restoration
·         Complete installation of topsoil and seed in areas of concrete replacement
·         Installation of sod in areas of storm sewer improvements.  

We thank you in advance for any inconvenience the work will create.