Work Completed Last Week:
Concrete Curb & Gutter and Sidewalk Replacement (Schroeder & Schroeder):
·         Estate Lane - Remove forms and install topsoil and seed

 Storm Sewer Improvements (DiVinci)
·         Huber Court – Install new frame and grate
·         Church Street – Remove and replace storm manhole. 

Asphalt Pavement Paving (JA Johnson Paving)
·         Huber Court – Huber Lane to East End
·         Greenbriar Drive – Lotus Lane to Warren Road (2nd Layer)
·         Country Lane – Central Parkway to Longvalley Road
·         Larch Avenue

Work Anticipated Next Week:
Concrete Curb & Gutter Replacement (Schroeder & Schroeder):
·         Huber Court – Huber Lane to East End

Storm Sewer Improvements (DiVinci)
·         No work anticipated

Asphalt Pavement Paving (JA Johnson Paving)
·         Church Street – Glenview Road to Dewes Street
·          Harmony Lane – Waukegan Road to west end (2nd Layer)

Landscape Restoration
·         Complete installation of topsoil and seed in areas of concrete replacement
·         Installation of sod in areas of storm sewer improvements.

 We thank you in advance for any inconvenience the work will create.