Monday, June 29, 2015

Majority of Asphalt Paving Now Completed.

Work Completed Last Week:

Asphalt Pavement Paving (JA Johnson Paving)
·         Church Street – Glenview Road to Dewes Street
·         Harmony Lane – Waukegan Road to west end (2nd Layer)

The majority of the work associated with the 2015 MFT project is now completed. The remaining work includes:
1)      Concrete curb & gutter along Huber Court
2)      Sod restoration in areas with storm sewer improvements.
3)      Clean-up at the project sites, as needed
4)      Repair minor deficiencies with work performed, as needed
5)      Repair areas of topsoil and seed, as needed

We appreciate the patience and understanding of all the residents who live along the roadways where work was performed this year. We understand there are many inconveniences that come with roadway work along your street or within your neighborhood.

 

Thanks again!!!!

Monday, June 22, 2015

Roadway Paving Continues

Work Completed Last Week:
Concrete Curb & Gutter and Sidewalk Replacement (Schroeder & Schroeder):
·         Estate Lane - Remove forms and install topsoil and seed

 Storm Sewer Improvements (DiVinci)
·         Huber Court – Install new frame and grate
·         Church Street – Remove and replace storm manhole. 

Asphalt Pavement Paving (JA Johnson Paving)
·         Huber Court – Huber Lane to East End
·         Greenbriar Drive – Lotus Lane to Warren Road (2nd Layer)
·         Country Lane – Central Parkway to Longvalley Road
·         Larch Avenue

Work Anticipated Next Week:
Concrete Curb & Gutter Replacement (Schroeder & Schroeder):
·         Huber Court – Huber Lane to East End

Storm Sewer Improvements (DiVinci)
·         No work anticipated

Asphalt Pavement Paving (JA Johnson Paving)
·         Church Street – Glenview Road to Dewes Street
·          Harmony Lane – Waukegan Road to west end (2nd Layer)

Landscape Restoration
·         Complete installation of topsoil and seed in areas of concrete replacement
·         Installation of sod in areas of storm sewer improvements.

 We thank you in advance for any inconvenience the work will create.

Friday, June 12, 2015

Remaining Storm Sewer Repairs, Concrete Curb & Gutter, and Asphalt Paving Scheduled for Next Week.

Work Completed Last Week:
Concrete Curb & Gutter and Sidewalk Replacement (Schroeder & Schroeder):
·         Completed concrete sidewalk and curb & gutter replacement on Mohawk Lane, Vantage Lane, and Greenbriar Drive
·         Greenbriar Drive - Driveway replacements
·         Church Street – Glenview Road to Dewes Street 

Storm Sewer Improvements (DiVinci)
·         No work completed.

Asphalt Pavement Paving (JA Johnson Paving)
·         Vantage Lane – Pfingsten Road to East End, including Cul-de-Sacs
·         Brookdale Lane – Landwehr Road to West End
·         Greenbriar Drive – Lotus Lane to Warren Road (1st Layer)
·         Harmony Lane – Waukegan Road to west end (1st Layer)

Asphalt Pavement Removal and Paving (JA Johnson Paving)
·         Alley north of Colfax Avenue, west of Waukegan Road.
·         Minor patching throughout the Village.

Work Anticipated Next Week:
Concrete Curb & Gutter Replacement (Schroeder & Schroeder):
·         Huber Court – Huber Lane to East End

Storm Sewer Improvements (DiVinci)
·         Huber Court – Huber Lane to East End
·         Church Street – Glenview Road to Dewes Street
·         Country Lane – Central Parkway to Longvalley Road 

Asphalt Pavement Paving (JA Johnson Paving)
·         Country Lane – Central Parkway to Longvalley Road
·         Church Street – Glenview Road to Dewes Street
·         Huber Court – Huber Lane to East End
·         Greenbriar Drive – Lotus Lane to Warren Road (2nd Layer)
·         Harmony Lane – Waukegan Road to west end (2nd Layer)

Landscape Restoration
·         Complete installation of topsoil and seed in areas of concrete replacement
·         Installation of sod in areas of storm sewer improvements.  

We thank you in advance for any inconvenience the work will create.

Friday, June 5, 2015

Roadway Resurfacing Throughout Village Continues

Work Completed Last Week:
Concrete Curb & Gutter and Sidewalk Replacement (Schroeder & Schroeder):
·         No work completed.

Storm Sewer Improvements (DiVinci)
·         Adjusted manholes along Vantage Lane.

Asphalt Pavement Removal and Paving (JA Johnson Paving)
·         Mohawk Lane – Indian Ridge Drive to Saranac Lane
·         Osage Drive – Indian Ridge Drive to West Cul-de-Sac
·         Minor Asphalt Patching at various locations throughout the Village. 

Asphalt Pavement Removal (JA Johnson Paving)
·         Brookdale Lane – Landwehr Road to West End
·         Vantage Lane – Pfingsten Road to East End, including Cul-de-Sacs
·         Greenbriar Drive – Lotus Lane to Warren Road
·         Country Lane – Central Parkway to Longvalley Road
·         Harmony Lane

Asphalt Patching (JA Johnson Paving)
·         Vantage Lane – Pfingsten Road to East End, including Cul-de-Sacs

Work Anticipated Next Week:
Concrete Curb & Gutter Replacement (Schroeder & Schroeder):
·         Complete concrete sidewalk and curb & gutter replacement on Mohawk Lane, Vantage Lane, and Greenbriar Drive
·         Greenbriar Drive - Driveway replacements
·         Huber Court – Huber Lane to East End
·         Church Street – Glenview Road to Dewes Street

Storm Sewer Improvements (DiVinci)
·         Huber Court – Huber Lane to East End
·         Church Street – Glenview Road to Dewes Street
·         Country Lane – Central Parkway to Longvalley Road 

Asphalt Pavement Paving (JA Johnson Paving)
·         Vantage Lane – Pfingsten Road to East End, including Cul-de-Sacs
·         Brookdale Lane – Landwehr Road to West End
·         Greenbriar Drive – Lotus Lane to Warren Road
·         Country Lane – Central Parkway to Longvalley Road
·         Harmony Lane 

Asphalt Pavement Removal and Paving (JA Johnson Paving)
·         MARS patching at various locations 

We thank you in advance for any inconvenience the work will create.

Monday, June 1, 2015

Pavement Removal and Paving to Begin this Week.

Work Completed Last Week:

Concrete Curb & Gutter and Sidewalk Replacement (Schroeder & Schroeder):
·         Osage Drive – Indian Ridge Drive to West Cul-de-Sac.
·         Mohawk Lane – Indian Ridge Drive to Saranac Lane.
·         Vantage Lane – Pfingsten Road to East End, including Cul-de-Sacs (Both sides for roadway)
·         Greenbriar Drive – Lotus Lane to Warren Road (Both sides of roadway).
·         Estate Lane – 100% Completed

Storm Sewer Improvements (DiVinci)
·         Mohawk Lane – Indian Ridge Drive to Saranac Lane.
·         Osage Drive – Indian Ridge Drive to West Cul-de-Sac.
·         Vantage Lane – Pfingsten Road to East End, including Cul-de-Sacs.
·         Greenbriar Drive – Lotus Lane to Warren Road.

Residents along Vantage Lane now have access to their driveways, as of Saturday, May 30th.

Work Anticipated Next Week:

Concrete Curb & Gutter Replacement (Schroeder & Schroeder):
·         Complete concrete sidewalk and curb & gutter on Mohawk Lane, Vantage Lane, and Greenbriar Lane.
·         Driveway replacements on Greenbriar Drive 

Storm Sewer Improvements (DiVinci)
·         No work anticipated

 Asphalt Pavement Removal and Paving (JA Johnson Paving)
·         Mohawk Lane – Indian Ridge Drive to Saranac Lane, including Mohawk CDS
·         Osage Drive – Indian Ridge Drive to West Cul-de-Sac
·         Brookdale Lane – Landwehr Road to West End
·         Vantage Lane – Pfingsten Road to East End, including Cul-de-Sacs
·         Greenbriar Drive – Lotus Lane to Warren Road
·         Minor Asphalt Patching at various locations throughout the Village.  

Parking will not be allowed on the street from 7am to 5pm during paving operations.

When pavement is coated with fresh oil and sand, please drive slowly to avoid it getting stuck to your cars.

Access may be limited for a short time as the asphalt is being placed in front of your driveways

Thank you for all your patience and understanding during the construction.